While construction of the tunnel is the centerpiece of Contract Package 1 – 1, the contract also includes construction of a 7.9 kilometer four (4)-lane road, three (3) pairs of bridges with a total length of 500 meters, two (2) underpasses, two (2) overpasses, a dozen box-culverts (waterways), and four (4) at-grade intersections.
The tunneling activity uses specialized equipment such as drill jumbo, concrete spraying machine and articulated dump hauler to excavate tunnel that has a diameter of 10 meters.
The on-going Contract Package 1-1 costing ₱13.23 Billion is financed by Special Terms for Economic Partnership (STEP) Loan between Philippines and JICA under loan agreement numbers PH-P261 and PH-P273.3